First, In consequence of the dovetailed form of the stones he required a crane that would drop them as nearly as possible on the beds on which they were permanently2 to rest.
Second, Supposing he devised a guy crane that overcame this difficulty, what was to be done as the building rose in height, and the guys became too nearly perpendicular3 to admit of such a crane being used?
In his private notes Mr. Stevenson regrets that he could get no advice from anybody he consulted, all of whom recommended him to employ common sheer poles, such as had been used by Smeaton at the Eddystone; and he adds, “I may say, morning, noon, and night, these difficulties have haunted me.” But thrown back on his own resources, and appreciating the difficulty as no one else could so well do, he found, as is often the case, that he was his own best counsellor, and he succeeded in solving the problem that had given him so much concern, by inventing what he called the “moveable beam182 crane,” and also the “balance crane,” which are shown in Plate XI. The former, as modified to suit particular cases, is now in universal use for building purposes, and the latter has been employed in rearing most of our Rock Lighthouses, so that I think professional readers will not object to my giving Mr. Stevenson’s description of these cranes, as designed by him at the beginning of this century. He says:—
“In cranes of the common construction the beam is a fixture4, and is placed at right angles to the upright shaft5: but in the machine represented in the Plate (Fig. XI-1), its attachment6 is at the lower extremity7 of the crane, where it is moveable up and down upon a journal or bolt. This crane is therefore termed a moveable beam crane. The moveable property of the beam, in so far as the writer knows, is new, and possesses the advantage of laying any stone within its range perpendicularly8 on its site. This, from the dovetailed form of the stones at the Bell Rock, rendered it particularly fitted for this work, to which a crane of the ordinary construction could hardly be said to be applicable. At the Eddystone Lighthouse this operation was performed by means of triangular9 sheers; but, from the greater extent of the Bell Rock works, and their greater depth in the water, such means must have rendered the process of building extremely tedious. These cranes were necessarily immersed at high water, and were retained in their places by four guys fixed10 at the top of the upright shaft, and the moveable jib or beam being lowered down, was secured to an eyebolt batted into the rock.”
PLATE XI.
MOVEABLE JIB and BALANCE CRANES.
W. & A. K. Johnston, Edinburgh.
183
“The ‘balance crane’ (Fig. XI-2) was constructed on a new principle for building the upper part of the Bell Rock Lighthouse, when the guy ropes of the moveable beam crane became ‘too taut,’ as sailors express it, or were too near the perpendicular, thereby11 rendering12 the beam cranes unstable13. To remedy this, the balance crane was so arranged as to be kept in equilibrium14 by a back weight of cast iron, so adapted as to counteract15 the varying load upon the working arm or beam. The elevation16 here represented is the same in principle with that used at the Bell Rock, but differs somewhat in form, agreeably to improvements made in order to adapt it to the erection of the Carr Rock Beacon17. The upright central column is a tube of cast iron put together in convenient lengths with flush joints18, after the manner of spigot and faucet19, fitted by turning and boring. The centre column of this machine might have been carried to any suitable or convenient height, by adding length to length, as the building advanced, without once moving the foot on which it rested, but at the Bell Rock not more than three lengths of from six to nine feet were generally in use. A malleable20 iron cross head was stepped into the void of the central shaft or column when the body of the crane was to be elevated. This operation was accomplished21 simply by hooking the main ‘purchase’ and ‘traveller’ chains into the eyes of the crosshead, when the machinery22 of the crane was employed with great facility as a locomotive power for lifting itself as each new length of central column was added. The weight of this crane as used at the Carr Rock did not exceed two tons.”
点击收听单词发音
1 perplexed | |
adj.不知所措的 | |
参考例句: |
|
|
2 permanently | |
adv.永恒地,永久地,固定不变地 | |
参考例句: |
|
|
3 perpendicular | |
adj.垂直的,直立的;n.垂直线,垂直的位置 | |
参考例句: |
|
|
4 fixture | |
n.固定设备;预定日期;比赛时间;定期存款 | |
参考例句: |
|
|
5 shaft | |
n.(工具的)柄,杆状物 | |
参考例句: |
|
|
6 attachment | |
n.附属物,附件;依恋;依附 | |
参考例句: |
|
|
7 extremity | |
n.末端,尽头;尽力;终极;极度 | |
参考例句: |
|
|
8 perpendicularly | |
adv. 垂直地, 笔直地, 纵向地 | |
参考例句: |
|
|
9 triangular | |
adj.三角(形)的,三者间的 | |
参考例句: |
|
|
10 fixed | |
adj.固定的,不变的,准备好的;(计算机)固定的 | |
参考例句: |
|
|
11 thereby | |
adv.因此,从而 | |
参考例句: |
|
|
12 rendering | |
n.表现,描写 | |
参考例句: |
|
|
13 unstable | |
adj.不稳定的,易变的 | |
参考例句: |
|
|
14 equilibrium | |
n.平衡,均衡,相称,均势,平静 | |
参考例句: |
|
|
15 counteract | |
vt.对…起反作用,对抗,抵消 | |
参考例句: |
|
|
16 elevation | |
n.高度;海拔;高地;上升;提高 | |
参考例句: |
|
|
17 beacon | |
n.烽火,(警告用的)闪火灯,灯塔 | |
参考例句: |
|
|
18 joints | |
接头( joint的名词复数 ); 关节; 公共场所(尤指价格低廉的饮食和娱乐场所) (非正式); 一块烤肉 (英式英语) | |
参考例句: |
|
|
19 faucet | |
n.水龙头 | |
参考例句: |
|
|
20 malleable | |
adj.(金属)可锻的;有延展性的;(性格)可训练的 | |
参考例句: |
|
|
21 accomplished | |
adj.有才艺的;有造诣的;达到了的 | |
参考例句: |
|
|
22 machinery | |
n.(总称)机械,机器;机构 | |
参考例句: |
|
|
欢迎访问英文小说网 |